WBS and the Deliverables Orientation: How to Implement the Same Tasks in Several Departments
5 minutes Posted Jul 18, 2011 at 5:00 pm.
0:00
5:55
Download MP3
Show notes
In this podcast, Ricardo talks about how to create a WBS. He explains that even though there are no specific rules to create a WBS, the most important thing is to allow the ones who will execute the work to fully understand what needs to be done. Ricardo also explains that the WBS does not provide any chronological sequence, but instead must guarantee that all the work to be produced is effectively broken down up to the point where the activities can be assigned to those who will execute them.